Banting Data Centre Power 2026: Why 275kV Infrastructure Matters for Industrial Land

A RM72.84 million 275kV power connection is being built for Banting Technology Park. Understand what this means for data-centre land and power-ready industrial sites in Selangor.

By Alvin Chin · · · 3 min read

Malaysia data-centre industrial ecosystem infographic showing opportunities for power and switchgear suppliers, cooling companies, engineering firms, fibre providers, cybersecurity companies and logistics operators in Selangor and Negeri Sembilan

Banting's data-centre story reached an important milestone in September 2026

On 18 September, Jati Tinggi Group secured a RM72.84 million contract to build a 275kV power connection between PMU Megasteel and a consumer landing station serving a data centre at Banting Technology Park. The Edge Malaysia

The project involves two underground and overhead 275kV circuits, transmission towers and associated infrastructure, with completion scheduled for January 2027.

That distinction matters when evaluating industrial land.

A nearby PMU does not make land power-ready

Industrial property discussions frequently use distance to a PMU as shorthand for electricity availability. Technically, these are different questions.

A viable high-power site must establish:

A PMU several kilometres away may be useful, but it does not prove that sufficient unused capacity exists.

What the Banting contract demonstrates

The RM72.84 million contract provides a practical example of the infrastructure between the national grid and a major data-centre campus.

In simplified form:

Transmission grid → PMU → high-voltage cable → consumer landing station → data-centre electrical infrastructure.

Jati Tinggi had already secured a separate RM69.16 million 33kV interim-power infrastructure contract at Banting Technology Park. The Edge Malaysia

This illustrates another important site-selection issue: permanent high-capacity electricity infrastructure can require substantial construction and time.

Malaysia data-centre supply chain in September 2026 showing hyperscale facilities alongside electrical equipment, cooling systems, engineering, fibre and logistics infrastructure

Why energisation date can matter more than land price

Suppose two industrial sites cost materially different amounts per square foot.

The cheaper site may appear preferable.

But if it requires significantly longer to secure power, the developer may incur:

For data centres, time-to-power can therefore outweigh the initial land-price difference.

artist impression of 1 acre industrial park in jenjarom selangor
View full size

Banting's wider industrial-property implication

The Banting Technology Park infrastructure does not mean every industrial parcel in Banting has equivalent power access. Each site requires independent utility assessment.

However, physical investment in high-voltage infrastructure strengthens Banting's broader position within Selangor's emerging digital-infrastructure geography.

It can also create secondary demand from companies supporting data centres, including:

These businesses generally require much smaller sites than hyperscalers.

How to assess power-ready industrial land

Before acquiring land for a high-power project, developers should establish:

Required load: How many MW are needed at full build-out?

Available capacity: What can realistically be supplied?

Voltage: Will the connection be 33kV, 132kV, 275kV or another configuration?

Infrastructure: What substations, cables and transmission works are required?

Redundancy: Does the proposed configuration meet operational resilience requirements?

Timeline: When can permanent power actually be energised?

Only then should land price become a primary comparison.

Practical takeaway

The Banting project demonstrates why data-centre land should be evaluated as an infrastructure package, not simply acreage.

For high-power developments:

Power nearby is not the same as power deliverable.

The strongest industrial sites will increasingly be those where developers can establish not only how much electricity is required, but how it reaches the property and when it becomes available.

Companies evaluating industrial land for data centres or high-power facilities in Selangor can contact Alvin Chin to discuss site requirements, land size, location and utility considerations.

Have a question about the market?

WhatsApp Alvin — he'll give you a straight read on pricing, availability and what's moving in your corridor.

Ask Alvin on WhatsApp

More insights